VALLEY CITY, N.D. ( Streets surrounding the Valley City water treatment plant are beat up and the city will spend $100,000 for paving reconstruction.
City Administrator David Schelkoph says the total project is estimated at $150,000.

Schelkoph says one of the contractor, Swanberg Construction who worked on the water treatment plant renovation will kick in $50,000.

The city commission approved of spending $100,000 from the Repair and Repaving fund for the project. Schelkoph says work will start next week and should be completed in about 3 weeks.