CITY, ND – (NewsDakota.com) A paving project will be start on Wednesday, August 24th in Valley City. Crews will be milling the streets and overlaying hot bituminous pavement over the milled surface.

The affected streets are listed below:

2nd Avenue NE from 2nd Street NE to 4th Street NE  will be closed to traffic on August 24th and 25th.

6th Street NE from Central Avenue to 8th Ave NE will be partially open to traffic on August 24th thru August 27th.

KLJ engineer and project manager Eric Gilbertson says vehicles should be parked off the street in these areas so the contractor will be able to complete their work.

Gilbertson says anyone with questions regarding these project should call the KLJ office in Valley City at 845-4980.